Currently we are preparing the excavation and concrete base for the 2nd workfield.
Reinforcement of the foundation slab of the 1st workfield.
Already finished:
-works connected with the 1st stage of excavations for the underground car park under the flats section and part of the microapartment section,
-constructing a Berliner-type retaining wall.
-securing the sides of the excavation with retaining walls
-demolition of production buildings and warehouses.